TURLOCK, Calif. — November 17, 2026. Turlock has completed its bid tabulation for a water-main replacement project on South Center Street and Crane Avenue. Ace-High Engineering submitted the lowest listed bid at $960,000 for project 24-022, according to a city engineering report dated November 12.
Approximately 1,677 feet of new water main
The city plans to install roughly 1,677 linear feet of PVC water main, connect customer service laterals along the route, retire existing water mains in place and restore excavated street trenches. That includes the associated work needed to return pavement and disturbed areas to safe use. The project is part of water infrastructure renewal, not a commitment to build a new water treatment plant.
Rolfe Construction Inc. submitted the next-lowest listed proposal at $1,014,573. United Pavement Maintenance submitted $1,067,113.08, and the rest of the evaluated bidders offered higher prices. The engineer's estimate was $1.1 million, meaning the lowest listed bid is below that estimate. This does not guarantee the final cost will equal the initial bid after any permitted changes.
Approval and construction still pending
The bid summary identifies December 8 as the anticipated City Council award date. Until council acts and a contract is signed, Ace-High is the low bidder, not necessarily the awarded contractor. The city's project listing does not give a verified shutdown schedule for individual household water services.
Residents should monitor official notices for work windows, traffic detours and any water service interruptions. The final contract, warranty and inspection documents will determine the project obligations.
Sources: Official City of Turlock November 12 bid tabulation, CP 24-022; Official city scope for Water Line Replacement on S Center and Crane Avenue.
Featured photograph: illustrative water pipe construction by David Klein / Unsplash, not South Center Street or Crane Avenue.
Support Turlock News
Choose how to support Turlock News:
Credit / Debit Card via StripeChoose your contribution amount on the secure California58 Stripe checkout. One-time support for independent local journalism.
Continue with PayPal Continue with ZelleZelle payments go to Vitaly Ataev Troshin. Please verify the recipient in your bank before sending. Availability depends on your bank.
Optional reader support. When possible, add “Turlock News” to the payment note. Contributions are not advertised as tax-deductible. Support does not influence editorial decisions.More from Turlock News
- Turlock Columbia Pool Ventilation and Gas-Line Work Draws $62,235 Low Bid →
- Turlock Geer Road Lane Closures Expected Into January as East Marshall Street Work Continues →
- Turlock Transit Area Paving Draws $120,740 Low Bid, Well Below $233,000 Estimate →
- Turlock Wastewater Plant Draws $15.70 Million Low Bid for Primary Flotator Overhaul →
- Turlock Council District 3 Still Undecided: Ryan Taylor Leads Cassandra Abram by Just 22 Votes →

COMMUNITY
Comments
Join the California58 conversation. You must be signed in to comment.
Create a free California58 account or sign in with an available social provider.