TURLOCK, Calif. — November 17, 2026. Turlock has received five construction proposals for a major overhaul at the Turlock Regional Water Quality Control Facility (TRWQCF). The city’s official November 10 bid tabulation lists Mountain Cascade, Inc., at $15,696,776.55 as the lowest bid for the Primary Flotator Improvements Project.
What will be repaired or replaced?
The capital project, CP 25-058, covers replacement of Pumps 3 and 4 at the primary influent pump station, rehabilitation of influent flumes, mechanical and pressure systems for two primary flotators, improvements to a sludge pump station and replacement of electrical equipment including motor control centers and programmable logic controllers. Additional grading, paving and drainage work is part of the published scope.
The second-lowest proposal was Syblon Reid at $15,755,106, followed by Cushman Contracting at $16,781,866.55, C. Overaa & Co. at $17,399,000 and GSE Construction at $17,518,900. The official bid tabulation lists an engineer’s estimate of $18 million.
Low bid does not mean award
City staff identify Mountain Cascade as the apparent low bidder, with a proposed council award date of December 8, 2026. That designation is subject to responsiveness review, contracting requirements and council action. It does not establish that work has started or that Turlock has already paid $15.7 million.
Residents can request the eventual executed contract, construction schedule and any planned service continuity measures. Wastewater upgrades matter for reliability, but the bid amount alone cannot establish future household sewer rates.
Sources: City of Turlock official November 10 bid evaluation, CP 25-058; Official capital projects list and work scope.
Featured photograph: illustrative industrial tanks by K. Mitch Hodge / Unsplash; not the Turlock treatment plant.
Support Turlock News
Choose how to support Turlock News:
Credit / Debit Card via StripeChoose your contribution amount on the secure California58 Stripe checkout. One-time support for independent local journalism.
Continue with PayPal Continue with ZelleZelle payments go to Vitaly Ataev Troshin. Please verify the recipient in your bank before sending. Availability depends on your bank.
Optional reader support. When possible, add “Turlock News” to the payment note. Contributions are not advertised as tax-deductible. Support does not influence editorial decisions.More from Turlock News
- Turlock Columbia Pool Ventilation and Gas-Line Work Draws $62,235 Low Bid →
- Turlock Geer Road Lane Closures Expected Into January as East Marshall Street Work Continues →
- Turlock Transit Area Paving Draws $120,740 Low Bid, Well Below $233,000 Estimate →
- Turlock Water Main Project Gets $960,000 Low Bid for South Center Street and Crane Avenue →
- Turlock Council District 3 Still Undecided: Ryan Taylor Leads Cassandra Abram by Just 22 Votes →

COMMUNITY
Comments
Join the California58 conversation. You must be signed in to comment.
Create a free California58 account or sign in with an available social provider.